Project
Bitterns Recycling — Field Piping Installation
Shark Bay Resources · Useless Loop, Western Australia
INTERNAL — GATE TO MOBILISATION

Mobilisation
Checklist

Document numberDTL-PRJ0072-CHK-001
RevisionA — project-specific (from DTL-OPS-CHK-0001)
JobDTL-PRJ0072 · Contract SBS10627 · PO 182113
MandatoryAll items ticked & signed before any team deploys to site. No mobilisation without a completed checklist.
This is the Shark Bay version of DTL’s mobilisation checklist. On top of our usual mobilisation items, it adds the extra gates the SBR contract requires before we go to site — every person’s medicals and clearances (SOW 7.5), the supervisor’s statutory approval (7.3), and SBR’s sign-off on the risk workshop and the hydrocarbon plan (7.6, 7.8). A standard checklist doesn’t include these, so this one is built specifically for this job. Per-person clearances are tracked on the Personnel Matrix (DTL-PRJ0072-HSE-002).
DTL (WA) Pty Ltd · ABN 45 677 646 454 · Commercial-in-Confidence
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 1 of 4
Mobilisation ChecklistBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-CHK-001
Rev A

1   Job & team set-up

 ItemEvidence / reference
Job / service number allocated in 2iB; recorded in Live Register (Scheduled)2iB
Contract & PO on file; PO 182113 confirmedSBS10627 / PO 182113
Documentation filed in SharePoint (contract, PO, this checklist)DTL – Operations – PRJ0072
Service roster submitted & approved; publishedOps Admin / Ops Mgr
Team members confirmed & assigned; substitutions notified
Team lead / site supervisor nominatedsee 7.3 gate below

2   Vehicle, equipment & tooling

 ItemEvidence / reference
Vehicle / plant pre-deployment inspection complete; defects rectifiedDTL-HSE-CHK-0002
All equipment, tooling & materials loaded (fusion gear, pumps, signage, first aid, spill kit)
Fuel & transport to/from site arranged
Plant & Equipment Register updated for the jobDTL-HSE-REG-0003
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 2 of 4
Mobilisation ChecklistBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-CHK-001
Rev A

3   Personnel gates — SOW 7.5, 7.2, 7.3, 7.4

 ItemEvidence / reference
Every person cleared on the Personnel Matrix (medical, D&A, police, tickets, VOCs)DTL-PRJ0072-HSE-002
SBR induction complete for all personnel & subcontractors (SOW 7.2)
Light-vehicle VOC held by anyone driving on site (SOW 7.2)
Nominated supervisor is Schedule 26 / Section 44 approved (SOW 7.3)evidence on file
Fitness-for-work briefed — SBR 0.00% BAC, on-arrival & daily D&A testing (SOW 7.4)

4   Safety, risk & approvals — SOW 7.6–7.8

 ItemEvidence / reference
CRAW held; controls reviewed & APPROVED by SBR (SOW 7.6)gates mobilisation
Project risk register issued from the CRAWDTL-HSE-REG-0006
JSAs / SWMS for first tasks completed & signedDTL-HSE-PRO-0001/0012
EH&S Management Plan approved by SBRDTL-PRJ0072-HSE-001
Hydrocarbon / waste procedure approved by SBR (SOW 7.8)DTL-PRJ0072-ENV-001
Necessary SBR permits prepared / submitted (SOW 7.1)
Traffic management plan in place (SOW 7.1, 7.7)DTL-PRJ0072-TMP-001
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 3 of 4
Mobilisation ChecklistBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-CHK-001
Rev A

5   Communications, emergency & commercial

 ItemEvidence / reference
Kick-off meeting with SBR booked / held (SOW 7.9)
Daily pre-start & weekly report templates readyDTL-PRJ0072-RPT-001
Emergency arrangements confirmed — contacts, muster, nearest medicalDTL-HSE-PRO-0006/0020
Financial tracker created & budget loaded; claim cycle understoodPayment Guide
Quality plan & ITP ready; weld records to start day oneDTL-PRJ0072-QMP-001 / ITP-001
Mobilisation gate. DTL does not mobilise until the CRAW controls are approved by SBR and the EH&S Plan, hydrocarbon procedure and personnel gates are complete.

Sign-off

COMPLETED — SITE SUPERVISOR
Name · Signature · Date
AUTHORISED TO MOBILISE — DTL
Tyson Knight, Director · Date
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 4 of 4